Pima County Tres Rios Wastewater Reclamation Facility
You are hereHome >All Projects > Pima County Tres Rios Wastewater Reclamation Facility
Using a CM-at-Risk delivery method, MWH is providing preconstruction and construction services to upgrade an existing pollution control facility. This fast-tracked project is scheduled for construction completion and commissioning by September 2013.
Expanding preliminary and primary treatment facilities from 37.5 to 50 mgd
Constructing a new 25-mgd ammonia/nitrogen/nutrient removal process system (5-stage Bardenpho) to replace an existing 25-mgd HPO train
Upgrade modification to existing 12.5-mgd BNRAS process train for additional ammonia/nitrogen/nutrient removal process system
Constructing a new 12.5-mgd capacity ammonia/nitrogen/nutrient removal process system
Modifying effluent disinfection facilities using sodium hypochlorite technology followed by de-chlorination
Constructing interim biosolids digestion and thickening improvements
Constructing biosolids facilities for additional sludge from an offsite 25-mgd water reclamation plant
Constructing miscellaneous ancillary support system improvements
Repairing and replacing wastewater equipment and structures
Expanding biosolids processing
Adding odor control measures
Upgrading the facility to be compliant with environmental, regulatory and building code requirements
MWH is self-performing approximately 50 percent of the work. MWH maintains exclusive control of the entire mechanical process equipment critical path, from procurement through operations. Our self-performance strategy is focused on the undivided ownership of the most complex aspect of the work, best ensuring an on time start up and completion.
While many CMAR contractors focus their self-performance on structural concrete, we know that is only half the path. Even though structural concrete does fall on the critical path during the initial phase of the work, the critical path ultimately runs directly through delivery of long lead equipment, mechanical process equipment setting and commissioning, instrumentation and controls and plant start up. To maintain maximum schedule and quality control, we self-perform the process equipment procurement, installation, instrumentation and control, and commissioning and start up.
The unfragmented control of late phase critical path activities provides the client with single point accountability at the place in the project most commonly responsible for the largest progress delays.
This project involves the expansion of treatment capacity from 37.5 to 50 mgd
Implementing Bardenpho technology
Repairing process units,
Replacing equipment and structures
Addressing odor control issues and upgrading the facility to be compliant with environmental, regulatory and building code requirements.
Equipment delivery that supports schedule milestones and construction sequence and re-sequencing should the need arise
Equipment procurement and installation benefited by operational review for control strategy reconciliation (with main plant control system), training and start up assistance, as needed to support schedule, spare parts consistent with client practices, certifications and warranty validation
In conjunction with client staff and the design professionals, we develop the control descriptions and screen layouts. We develop the control/SCADA system programming per the approved submittals and design documents