Did you know MWH is performing design and construction administration duties for a huge underground pumping station in Cleveland, Ohio?

The $73.2 million Easterly Tunnel Dewatering Pump Station is a 160mgd deep-cavern pumping station, 240 feet below ground that stores combined sewer overflows during peak wet weather events. Once flows subside, the facility will dewater the storage tunnels and pump flows into the Easterly Interceptor where it will be conveyed by gravity to the Easterly Wastewater Treatment Plant.

Read a case study on the project recently featured in Public Works magazine.

Easterly Tunnel Dewatering Pump Station

Easterly Tunnel Dewatering Pump Station